Scattered authority doomed HealthSMART

 

Public sector probity rules under fire.

The Victorian Government's $360 million whole-of-health IT modernisation was scuttled by a complex three-way delivery arrangement that devolved project responsibility, according to a pair of former iSOFT executives.

Appearing before the Victorian Parliament’s Public Accounts and Estimates Committee back in August, James Rice and Gary White — both now with CSC, after its buyout of iSOFT last year —revealed their thoughts on Victoria's HealthSMART initiative.

The official transcript of their appearance before the committee was released last week. (pdf)

iSOFT landed a contract to supply its i.Patient Manager (iPM) software to the HealthSMART initiative in 2005, delivering the software to 10 "lead agencies" that consisted of a mix of hospitals, health alliances and area health services.

Via CSC, iSOFT won a contract extension that went largely unfulfilled. HealthSMART was then abandoned in May this year.

iPM was but one of the IT pieces that went into the statewide HealthSMART solution.

White, who is now Asia Pacific operations director at CSC, attributed HealthSMART's problems to "the way the contract was set up".

Rather than "normal" arrangements where iSOFT would either act as prime contractor or as a sub-contractor to the prime, iSOFT had responsibilities to the overseeing HealthSMART organisation and then to the health alliances, hospitals and area health services that ended up with iPM software.

"I think one of the overall issues with HealthSMART as a program is that no one organisation was given the accountability to deliver the whole program," said James Rice, who is now CSC's healthcare group managing director.

However the quality of the staff and their capabilities were not an issue, the executives said.

Other alleged shortcomings revealed by White and Rice were that:

  • HealthSMART allowed the iPM software to fall behind by up to three releases, depriving lead agencies of much needed product enhancements.
  • Rolling out a common IT platform statewide was undermined by hospitals and agencies that insisted on separate customisations of the products before acceptance.
  • HealthSMART did not have the authority to drive resistant health services and hospitals to adopt the statewide system.
  • The functional specifications for the overall project were changed after software was already being customised.
  • The group approving functional specifications was not representative of all potential users and there was insufficient reviews to ensure the changes would satisfy users' needs in practice.

No love for probity

Shortcomings in the strict probity requirements of the original procurement also rated considerable discussion in the hearings.

“When dealing with the public sector, you end up doing a lot of enhancement work to satisfy all the people who have contributed to those requirements,” Rice said.

“It is very hard from a single sentence and a tick box where we say we complied to then deliver the software and have them say, ‘That was not actually what we meant’.

The more enhancements there are, the more risk there is to the project running smoothly, Rice said.

More generally Rice said that probity rules barred any frank discussion about varying the requirements into something that could be easier to deliver and better for the health agencies involved.

Such variations risked having the tender aborted and another one take its place incorporating the new requirement because the market should have the opportunity to bid for the varied specification.

“We went through a tender process, we were successful in being selected, we negotiated a contract and we have delivered everything in that contract,” Rice said.

“I do not think the customer is getting as much out of the software as they can, and I truly believe the client cannot point to why they did it or what benefit they are getting from it. That, to me, is a consequence of the way it was procured.”

Most health services slated to receive the HealthSMART system are now free to choose what systems they would like to run.

Copyright © iTnews.com.au . All rights reserved.


Scattered authority doomed HealthSMART
 
 
 
 
Top Stories
Review: Microsoft Surface Pro
A year is a long time in the computer hardware business.
 
NBN Co could miss revised June fibre targets
Analysis: Cutting it fine in the race to the line.
 
Review: Sydney's Opal smartcard
It's no Oyster card.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Vivek Kundra on Australia's 'cloud last' policy
Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Latest Comments
Polls
Will you quit any cloud services in light of PRISM?

   |   View results
Yes
  62%
 
No
  38%
TOTAL VOTES: 71

Vote