NBN Co's second corporate plan in numbers

 

The plan in fun-size.

NBN Co has released its much-anticipated second corporate plan (pdf), revising many of the numbers and assumptions in the 2010 version and updating it to reflect significant project scope changes.

Described by Communications Minister Stephen Conroy as "NBN Co's first operational plan", with forecasts "against which the network can be measured", the 96-page document comes in shorter than its 2010 equivalent, but with forecasts that are likely to prove much more accurate in determining the scope, extent and costs of the network over the next decade.

Here are the key takeaways:

Finances

NBN Co has indicated several factors — including construction delays, the unanticipated $800 million Optus deal and a move to opt-out construction — increased capital expenditure for the network by 3.9 percent, or $1.4 billion.

That brings the total network cost to $37.4 billion, over the originally assumed $35.9 billion.

The extra costs will be funded through faster government bonds. Conroy said there would be no "NBN tax" on Australians.

Operating expenditure has also increased $3.2 billion over the life of the project due to scope and "other changes", additional resources  required for community engagement, contract management, dealings with Telstra and IT management.

However, NBN Co noted savings in OpEx, which it attributed to "futher network planning and design" of the fixed wireless and satellite networks.

NBN Co has forecast an earnings loss of $3.3 billion over the network construction period, largely since operating expenditure, at $26.4 billion, will exceed revenues, at $23.4 billion, over the decade.

Government funding for the network, which reached $1 billion for 2011, is expected to peak at $6.6 billion during 2015, amounting to a total $30.4 billion over the life of the project. The remainder of the funding, just above a third of the total, will come from debt markets.

The internal rate of return on government equity has also been revised up from seven percent in the previous corporate plan, to 7.1 percent.

Take-up

Despite significant changes to the scope of the project, the number of premises NBN Co expects to pass and connect over the next decade hasn't changed all that much.

NBN Co will still pass 12.2 million premises with fibre, with 8.5 million of those expected to connect to the network by June 2021; up 200,000 from the previous corporate plan.

Some 500,000 of those users will come from the Optus deal to migrate customers off its cable networks, a process that is expected to take until 2020.

A further million will end up with available fixed wireless or long-term satellite connections by the end of the network's construction, but only 200,000 — or a conservative 20 percent — are forecast to take up a service in that same timeframe.

NBN Co CEO Mike Quigley acknowledged the take-up rate was conservative as a result of mobile technologies in regional and rural areas that NBN Co expects will compete more heavily with NBN technologies than in fibre areas.

Unlike the previous corporate plan, the company hasn't broken out its passing/activation numbers for satellite and fixed wireless, potentially as a result of continuing resistance in some areas to the construction of fixed wireless towers.

But take-up of the wireless technologies is important for all NBN subscribers, as it will indicate how quickly the company can reduce wholesale prices across the network over time. Quigley confirmed the cost per subscriber does depend on this take-up: "The more customers you get on those, the lower the cost per subscriber for the fixed cost you've got".

Communications Minister Stephen Conroy took the release of the corporate plan to defend NBN's ongoing challenges with greenfields estates.

He, and the corporate plan, both note that NBN Co had severely fallen short of initial forecasts for building in new developments due to unclear obligations between NBN Co and Telstra, the previous provider of last resort for telecommunications services.

"It was assumed that NBN Co would accept applications from developers for  greenfields estates that had commenced Stage 5 civil works construction prior to 1 January 2011," the corporate plan states.

NBN Co subsequently "handed back" 70,000 to 100,000 premises for Telstra to complete connections, while initial forecasts on the number of developer applications the company has received fell short by 40,000 as of June 30 this year.

Fibre build

NBN Co has revised the fibre build required for the National Broadband Network, indicating it will use more Telstra exchange space and dark fibre than initially envisaged, while increasing the amount of physical fibre the company will roll out to homes.

Under the revised corporate plan, NBN will roll out a total 206,000 kilometres of fibre, covering 148,000 kms of "covered road distance", up from 181,000 kilometres and 130,000 kilometres, respectively.

The new distances, the corporate plan states, also come as a result of the move from the original, blue fibre to green ribbon cables.

One contentious change to the fibre build in the new corporate plan is the move to 'build drops', meaning NBN Co will automatically connect fibre from the street to a premises, requiring the user to opt out of an installation, rather than opt in as previously.

A network termination device is then installed inside the house once a user orders an NBN connection through a service provider.

IT builds

NBN Co now runs over 2000 servers and 500 databases hosted in Global Switch's Sydney facility and Queensland's Polaris facility for its operational and business support systems.

The move to fully automated operational support systems is ongoing under a $200 million contract with an IBM-led consortium, including three product releases scheduled for this year.

These will introduce automation for the new 'build drop' capability, implementation of requirements from the Telstra deal, external workforce management and support for new multicast and small business product releases.

"The operation of the NBN Co network, including activation and assurance transactions, will be highly automated through progressive capability being delivered by the OSS programme," the plan states.

"Progressive OSS capability releases will enable Access Seekers to monitor their services and operationally support their End-Users."

NBN Co did not break out actual IT costs other than to say it was an "additional cost".

Copyright © iTnews.com.au . All rights reserved.


NBN Co's second corporate plan in numbers
 
 
 
Top Stories
Frugality as a service: the Amazon story
Behind the scenes, Amazon Web Services is one lean machine.
 
Negotiating with the cloud email megavendors
[Blog post] Lessons from Woolworths’ mammoth migration.
 
Qld govt to move up to 149k staff onto Office 365
Australia's largest deployment, outside of the universities.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

The great data centre opportunity on Australia's doorstep
The great data centre opportunity on Australia's doorstep
Scott Noteboom, CEO of LitBit speaking at The Australian Data Centre Strategy Summit 2014 in the Gold Coast, Queensland, Australia. http://bit.ly/1qpxVfV Scott Noteboom is a data centre engineer who led builds for Apple and Yahoo in the earliest days of the cloud, and who now eyes Asia as the next big opportunity. Read more: http://www.itnews.com.au/News/372482,how-do-we-serve-three-billion-new-internet-users.aspx#ixzz2yNLmMG5C
Interview: Karl Maftoum, CIO, ACMA
Interview: Karl Maftoum, CIO, ACMA
To COTS or not to COTS? iTnews asks Karl Maftoum, CIO of the ACMA, at the CIO Strategy Summit.
Susan Sly: What is the Role of the CIO?
Susan Sly: What is the Role of the CIO?
AEMO chief information officer Susan Sly calls for more collaboration among Australia's technology leaders at the CIO Strategy Summit.
Meet the 2014 Finance CIO of the Year
Meet the 2014 Finance CIO of the Year
Credit Union Australia's David Gee awarded Finance CIO of the Year at the iTnews Benchmark Awards.
Meet the 2014 Retail CIO of the Year
Meet the 2014 Retail CIO of the Year
Damon Rees named Retail CIO of the Year at the iTnews Benchmark Awards for his work at Woolworths.
Robyn Elliott named the 2014 Utilities CIO of the Year
Robyn Elliott named the 2014 Utilities CIO of the Year
Acting Foxtel CIO David Marks accepts an iTnews Benchmark Award on behalf of Robyn Elliott.
Meet the 2014 Industrial CIO of the Year
Meet the 2014 Industrial CIO of the Year
Sanjay Mehta named Industrial CIO of the Year at the iTnews Benchmark Awards for his work at ConocoPhillips.
Meet the 2014 Healthcare CIO of the Year
Meet the 2014 Healthcare CIO of the Year
Greg Wells named Healthcare CIO of the Year at the iTnews Benchmark Awards for his work at NSW Health.
Meet the 2014 Education CIO of the Year
Meet the 2014 Education CIO of the Year
William Confalonieri named Healthcare CIO of the Year at the iTnews Benchmark Awards for his work at Deakin University.
Meet the 2014 Government CIO of the Year
Meet the 2014 Government CIO of the Year
David Johnson named Government CIO of the Year at the iTnews Benchmark Awards for his work at the Queensland Police Service.
Q and A: Coalition Broadband Policy
Q and A: Coalition Broadband Policy
Malcolm Turnbull and Tony Abbott discuss the Coalition's broadband policy with the press.
AFP scalps hacker 'leader' inside Australia's IT ranks.
AFP scalps hacker 'leader' inside Australia's IT ranks.
The Australian Federal Police have arrested a Sydney-based IT security professional for hacking a government website.
NBN Petition Delivered To Turnbull's Office
NBN Petition Delivered To Turnbull's Office
UTS CIO: IT teams of the future
UTS CIO: IT teams of the future
UTS CIO Chrissy Burns talks data.
New UTS Building: the IT within
New UTS Building: the IT within
The IT behind tomorrow's universities.
iTnews' NBN Panel
iTnews' NBN Panel
Is your enterprise NBN-ready?
Introducing iTnews Labs
Introducing iTnews Labs
See a timelapse of the iTnews labs being unboxed, set up and switched on! iTnews will produce independent testing of the latest enterprise software to hit the market after installing a purpose-built test lab in Sydney. Watch the installation of two DL380p servers, two HP StoreVirtual 4330 storage arrays and two HP ProCurve 2920 switches.
The True Cost of BYOD
The True Cost of BYOD
iTnews' Brett Winterford gives attendees of the first 'Touch Tomorrow' event in Brisbane a brief look at his research into enterprise mobility. What are the use cases and how can they be quantified? What price should you expect to pay for securing mobile access to corporate applications? What's coming around the corner?
Ghost clouds
Ghost clouds
ACMA chair Chris Chapman says there is uncertainty over whether certain classes of cloud service providers are caught by regulations.
Was the Snowden leak inevitable?
Was the Snowden leak inevitable?
Privacy experts David Vaile (UNSW Cyberspace Law and Policy Centre) and Craig Scroggie (CEO, NextDC) claim they were not surprised by the Snowden leaks about the NSA's PRISM program.
Latest Comments
Polls
Which bank is most likely to suffer an RBS-style meltdown?





   |   View results
ANZ
  20%
 
Bankwest
  9%
 
CommBank
  11%
 
National Australia Bank
  17%
 
Suncorp
  24%
 
Westpac
  19%
TOTAL VOTES: 1440

Vote