NBN rollback to cost at least $1.8 billion

 

Network harder to cancel, Budget documents reveal.

The Federal Government has revealed taxpayers would be liable for at least $1.8 billion, should the National Broadband Network project be culled in the future.

Risk statements (pdf) released with the 2012-2013 Budget overnight revealed the figure as a termination liability for the $27 billion project as at the end of March this year.

It indicated the Government's equity funding agreement with NBN Co commits it "in the event of a termination of the NBN roll out, to provide sufficient funds to NBN Co to meet its direct costs arising from the termination".

The liability assessment comes as the Coalition continues to consider its policy position on the NBN in the event it takes power at the next election.

Given that election is due for November 2013, termination liabilities for the network are likely to be significantly higher than the $1.8 billion detailed in budget papers last night.

Although it has not fully detailed its policy, the Coalition is known to be reconsidering the rollout of fibre to 12 million homes in favour of a more technologically agnostic mix of copper, cable, wireless and satellite.

Areas already connected to the NBN at the time of a Coalition victory would remain on the network but forward-looking rollout plans at that time remain uncertain. NBN Co has committed to have work "underway or completed" at 3.5 million homes by 2015.

Shadow communications minister Malcolm Turnbull would conduct a cost-benefit analysis of the current project, with an aim to potentially renegotiate major contracts and cancel some agreements where financially viable.

Telstra CEO David Thodey told the Coalition last month that a future government would not have to completely rewrite contracts hatched between Telstra and NBN Co in order to facilitate a revised NBN model.

The incumbent telco has an $11 billion deal to provide NBN Co with access to its pit-and-pipe infrastructure and for the migration of Telstra's copper and cable broadband customers onto NBN fibre.

The Federal Government indicated NBN Co's liabilities to Telstra under that agreement currently sat at approximately $209 million, though they would increase "progressively during the roll out of the network".

NBN Co is obligated to pay a termination fee of $500 million to Telstra if the contract is cut after the network has reached more than 20 percent of premises.

Turnbull refused to comment on the liability assessment this morning but Liberal sources referred to the inclusion of the figure in budget papers an attempt by the current Government to make a "political straw-man" of the Coalition's broadband policy and curry favour with voters.

Prime Minister Julia Gillard has repeatedly pointed to the differences between Labor and Coalition policies on the NBN as a choice between "broadband or no broadband".

Legal rollback

An assessment of a future Coalition government's ability roll back Labor legislation surrounding the NBN has also provided a bleak view of any future attempts to roll-back current plans.

Corrs Chambers Westgarth special counsel Andrea Kennedy, writing for legal monthly Internet Law Bulletin, said any change to the plans would "require the Coalition to assess the Government and NBN Co's ability to modify existing contractual arrangements".

She pointed to a requirement to repeal or modify complex regulatory arrangements in Parliament, as well as those enacted by the competition watchdog in anticipation of the network being built as currently planned.

"Exactly what aspects of Labor's NBN legislation would be changed is uncertain," she said.

"It is unclear how the retention of the [Telstra structural separation] fits with the Coalition's intentions for Telstra's HFC network. And presumably other NBN regulation would need to change."

Kennedy noted that future legislative change would likely require support from the Greens, which has typically supported the current NBN model, potentially forcing "political compromises" from the Coalition.

She said the issues were "surmountable" but that "legal and contractual constraints may mean that at least some aspects of the current NBN reforms will manage to survive" under a future non-Labor government.

Copyright © iTnews.com.au . All rights reserved.


NBN rollback to cost at least $1.8 billion
 
 
 
 
Top Stories
ATO commits to complexity
Greater demand, fewer apps.
 
Photos: AusCERT 2013 day two
The second day of the Queensland security conference.
 
The illusion of cognitive computing
Opinion: IBM's Watson is a marketing success.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: ING Direct [The Benchmark Awards]
Judges notes: ING Direct [The Benchmark Awards]
iTnews' panel of judges discuss ING Direct's 'Bank in a Box', one of three shortlisted finalists for the banking and finance category of the CIO Benchmark Awards.
Judges notes: Yarra Valley Water [The Benchmark Awards]
Judges notes: Yarra Valley Water [The Benchmark Awards]
iTnews' panel of judges discuss Yarra Valley Water's insourcing project, one of three shortlisted finalists for the Utilities category of the CIO Benchmark Awards.
Latest Comments
Polls
Do you prefer the Coalition's NBN policy?

   |   View results
Yes
  19%
 
No
  81%
TOTAL VOTES: 1727

Vote