NSW Health has identified issues with configuration, training and support of its FirstNet clinical information system (CIS) following a government-commissioned independent review.

Implementation of the Cerner FirstNet CIS began in 2008, and was expected to improve information management in more than 200 emergency departments across the state.

But clinicians resisted the change, leading NSW Health Minister Jillian Skinner to engage Deloitte consultants earlier this year for an independent review.

A NSW Health spokesman this week said that the Director-General was currently considering a draft report from the review.

“As with all major IT projects, there have been implementation issues,” the spokesman said.

“It is expected that the review recommendations will lead to a comprehensive program to address issues raised in the review process.”

The review included consultation with University of Sydney academic Jon Patrick, and Sally McCarthy, president of the Australian College of Emergency Medicine.

In March, Patrick published a 190-page analysis of the FirstNet roll-out, including feedback from emergency department directors and software performance experts.

McCarthy told the Health Informatics Conference in Brisbane on Tuesday that 98 percent of clinicians’ feedback in the Deloitte review was negative.

The CIS displayed information in non-intuitive ways, called for irrelevant inputs (like asking if a male patient was pregnant), and was unstable, she said.

She added that FirstNet had decreased the productivity of some senior staff by up to 40 percent, and redirected doctors’ attention from patients to a computer program.

Clinicians also complained of a lack of support that caused change requests to take “months or sometimes years to resolve”, McCarthy said.

Patrick explained that Cerner had designed the software so that any surface-level changes also required changes to be made at a structural level.

“It’s unmanageable,” he said. “Staff don’t know where to make a change, administrators afraid to make a change because documentation is unreliable or out of date.

“It’s [NSW Health service provider] Health Support Services and Cerner that come together and create the problem. Everyone loses despite what the technocrats say.”

‘If you don’t vote, you don’t get to complain’

Cerner executive Judy Van Norman said she was not involved in the NSW deployment, but speculated that too few clinical staff participated in the design process.

She told the conference that successful e-health “clinical transformations” required changes to be made to an organisation’s technology, culture, practices and workflow design.

Change should be led be an executive leader, dedicated clinical leaders, stakeholder champions and informal leaders, and supported by strong governance processes, she said.

“Sometimes the people who are most vocal are the people who didn’t invest their time and then show up later and want to shoot holes in the decisions that were made,” she said.

“I call that a ‘if you don’t vote, you don’t get to complain’ kind of syndrome.”

NSW Health’s spokesman said FirstNet was selected “using a process led by clinicians and actively involving clinicians who would be users of the system”.

FirstNet has been deployed in nearly 60 NSW hospitals to date, and managed information about admissions, vacant beds, patient waiting times and the availability of medical test results.

It was part of stage one of the state’s electronic medical record (eMR) program, which aimed to replace paper records with online records about a patient’s care in hospital.

“Unlike the earlier emergency department standalone IT systems, the FirstNet software requires more clinical information to be entered,” the spokesman said.

“This data now forms a foundation element of the broader electronic medical record for the patient throughout their care across the hospital and across care settings.

“It will also provide an essential contribution to the ability of the NSW eMR to interact with the planned national electronic health record through the provision of electronic discharge summaries and other care summaries.”

Stage two of the eMR program was expected to commence next year and extend the electronic system to outpatient and ambulatory care settings.

Implementation of a new critical care clinical information system would also commence in 2012, together with the first phase of electronic medication management.

Antony Sara, CIS director of the South Eastern Sydney and Illawarra Area Health Service, noted that issues with the FirstNet module did not extend to other eMR program aspects, including Cerner’s SurgiNet and PowerChart products.

However, he noted that “times of change is when errors happen”, and called for electronic and paper forms that “look the same in content and flow”.

Copyright © iTnews.com.au . All rights reserved.


 
 
 
 
Top Stories
CenITex to move from IT provider to broker
Documents reveal new strategy.
 
eHealth measures missing the point
Opinion: When will the PCEHR lead to patient outcomes?
 
Photos: Google Glass gets real
Coming soon to an office near you.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: ING Direct [The Benchmark Awards]
Judges notes: ING Direct [The Benchmark Awards]
iTnews' panel of judges discuss ING Direct's 'Bank in a Box', one of three shortlisted finalists for the banking and finance category of the CIO Benchmark Awards.
Judges notes: Yarra Valley Water [The Benchmark Awards]
Judges notes: Yarra Valley Water [The Benchmark Awards]
iTnews' panel of judges discuss Yarra Valley Water's insourcing project, one of three shortlisted finalists for the Utilities category of the CIO Benchmark Awards.
Latest Comments
Polls
Do you prefer the Coalition's NBN policy?

   |   View results
Yes
  19%
 
No
  81%
TOTAL VOTES: 1689

Vote