Dear Mr Thodey: You won't save money this Christmas

 

A guest column from a Telstra contractor.

Dear Mr Thodey,

I refer to Telstra's decision to stand down contractors for seven weeks over Christmas and New Year.

I am writing to tell you that this will not save Telstra a cent in the long run.

I am currently a contract hire at Telstra and therefore intimately impacted by this decision. But I also have some insights that you should consider.

The explanation given by a Telstra spokesperson to iTnews is shallow, misleading and in no way explains the lack of valid justification.

This is a short-term strategy.

Good management identifies what projects are successful and what projects are not working and acts accordingly on a case-by-case basis. If a project's business case doesn't stand up, you scoff it. But you don't weasel out of making these decisions and just opt for a blanket shutdown.

The majority of the contract labour at Telstra has been engaged for new development of product or services with the object of maintaining or enhancing Telstra's position in the marketplace.

Each of these projects must have an approved business case in order to engage labour. Time to market is a major factor in establishing a return on investment to support the business case.

It is the project manager's responsibility on approval of a business case to engage resources to deliver the new/enhanced product or service within the stipulated timeframes.

Standard practice is to initially engage permanent staff and if no suitable candidate is available, seek approval to raise a SoW [Statement of Work] for hiring a contract labour resource. In some areas of Telstra, the approval process can take in excess of three months for final endorsement.

Here is where the decision to stand down contractors starts to fall apart.

Seven weeks might look good on paper, but a large majority of the contract hires would have taken a two to three week break over the Christmas/New Year period, as do a large number of permanent employees. As a consequence the perceived cost saving for Telstra is reduced to less than four weeks.

But more importantly, permanent employees only have four weeks paid annual leave per annum and will be back at work well before the expiry of the stand-down period.

As project teams have inter-dependencies between contractors and permanent staff this will be a period of negligible productivity as permanent staff wait on the contractors to return to provide them with what they need to make their contribution.

Consider, for example, a case in which a lead architect of a project has to stand down, and perhaps goes looking for work elsewhere as a result (Very few people can afford that hit on their finances at such short notice).

Meanwhile, 50 or 60 other permanent staff cannot proceed with their tasks without the architect having finished their job. If that architect finds other work and doesn't return, we then have several months to wait under the new hire freeze before we can replace him.

I can assure you, as soon as the stand-down period was announced; contract staff were out in the market seeking alternate opportunities. This typically results in losing the higher quality contractors to other hirers. A bank in Melbourne happened to be inundated with enquiries about contract project management roles...

Each realised flight risk incurs further delay and expense through having to re-engage resources through the SoW approval process and additional productivity lost while the new hire climbs the learning curve.

Those SoW expiring end of December will need to have any extensions approved - which is unlikely until at least February [2011].

As soon as the announcement was made, non-contract project staff went into contingency mode, seeking exemptions inhibiting any further project progress.

Several projects immediately called out a three month delay to their projects comprising three weeks leading up, seven weeks duration plus a minimum three weeks to re-engage.

So does that save money? One project manager took the time to do a cost-benefit analysis impact of this action.

Allowing for the maximum saving over seven weeks it showed a $5 million reduction in Telstra spend. Again, that looks good on paper.

But unfortunately his business case took a $25 million hit as a consequence of this decision.

It doesn't seem to be understood that management agreed to spend this money because there is an expectation of a long term return on investment. Delays endanger that return.

As an aside, one unintended benefit of this decision is that it has universally united middle to lower upper management against it, because of its Dilbertesque absurdity. Director and General Manager-level executives are even embarrassed by it.

As a contractor I accept that there is an inherent lack of security of my tenure.

But I am also incensed by the lack of concern regarding the welfare of a group of generally loyal contributors based on a decision that would not stand scrutiny as a business case.

If we accept that this decision will show a short-term saving, where the real cost will not become apparent until the next financial year and will be to the detriment of the company and shareholders in the long term, then a reasonable person would ask questions on the motivation behind imposing an unnecessary financial hardship on contractors leading up to the Christmas period.

It strikes me that one of your executives is merely manipulating the books in the short-term for want of a better bonus.

-- Name withheld.

Copyright © iTnews.com.au . All rights reserved.


Dear Mr Thodey: You won't save money this Christmas
"The letter is well written, true and correct but it misses the point. Telstra is only interested in their shareholders. Anything that increases the profit, by slashing costs, management will do. ..."
By marcusg
 
 
 
Comments: 13
rninne
Dec 2, 2010 9:56 AM
One of the best open letters I have read this year. I admire the writer's restraint in building a case for his argument before pointing out the blatantly obvious reason for the stand down.

I hope this decision is reversed. I whole heartedly sympathise with the position of the contractors, I know how I would feel if I was in a similar position, I probably wouldn't have shown as much restraint.

~Robert
Raj
Dec 2, 2010 10:26 AM
Mr Thodey deployed the same approach his ex-employer IBM was doing many years ago and is still doing now....stand-down contractors to meet the financial forecast, re-hire the same contractors at higher rate 3-6 months later, then get rid of these high paid contractors as a priority when labour market is more conducive (or better still completely abolish the job here in Australia and outsource).
It is trend...... a sad one indeed.
Rossyduck
Dec 2, 2010 11:19 AM
Usual short term telco view with the last line summing it up neatly. A pity shareholders approve incentive packets based on a year - few people seem to understand that a years accounting period is artificial and is purely for convenience, not to run a sustainable business by.

On the other hand probably hoping for some high attrition and can then outsource the entire project overseas, or just leave it to NBN Co.
Nick
Dec 2, 2010 11:37 AM
I agree with rninne, great restraint shown. As a Telstra contractor myself I will be severely impacted by this decision. David Thodey talks of respect for each other and professional behaviour, is this what has been demonstrated by this action?
Popatopher
Dec 2, 2010 12:36 PM
Could not have said this any better myself.
The area I am working in has 4 employees and 30+ contractors. This will not only bring Capexed Project work to a grinding standstill but it will impact the Vendor delivering. This vendor will, due to a lack of work coming from Telstra, and an inability to answers to from Telstra move staff onto other clients (i.e. like the new big outsource contract they have just signed with a major bank)
Of the 10 contractors I directly work with every single one has started seeking alternate contract work. 4 had interviews this week.
The huge loss of IP in this mass exodus will, IMHO, have minimum 6 month impact on delivery timelines for projects. Replacement Contractors - if they can find them, will need to come up to speed with the poorly documented process and procedure they use for new build capability.
What has not been mentioned in this article is the other "Savings Initiatives” lined up with this. Telstra are reviewing all roles and defining new Contractor Rate cards based on external advice from a consultancy. This consultancy has tendered rate cards that are so far from the market norm (they have admitted they have some faulty data) that this will further drive out existing contract resources from Telstra ranks. Not only this, but Telstra naively believe that that they can replace a significant number of contractors with Permanent staff.
So they have implemented a stop on SOW renewals and blocked any new contract hires. When it comes to the time (February) to re-engage - New SOW's will be competed for firstly by applications for permanents, only after this will they be allowed to seek contract roles. Imagine the delays this will add into the project delivery timelines as resources are not allowed to be replaced.
Clearly the people driving a $ driven bottom line cost reduction are not connected to the rewards of delivering projects on time and on budget. Maybe the fundamental is Telstra has settled on is that it simply has too many people for the diminishing market share it fears.
I say to David Thodey - "believe you will have a diminishing market share and that’s what you will get - you will by taking this approach remarkably exceed your expectations - your rate of loss of market share will accelerate beyond belief as you fail to deliver project after project that gives you capability to overcome your current high customer dissatisfaction.
Your competitors will rush to expand the products and service offerings driven by the remarkable influx of new customer above their forecast levels and no doubt, they will be funding new projects requiring the very same skills Telstra are letting out on to the market place.
Mordd
Dec 2, 2010 3:54 PM
I congratulate the author of this letter for speaking out and explaining why this is such a short-sighted and stupid decision by Telstra. This is a classic case of too much bureaucracy and executives making decisions without properly understanding the full impact of those decisions. Apart from the financial losses explained in the above letter, Telstra risks losing further customers as a result of this decision as this is just yet another example to the community of Telstra treating its workforce like sh*t. If they don't care about their employees, do you really think they give a flying f*ck about their customers? "Not likely" is the message that goes out.
LM
Dec 3, 2010 4:28 PM
One overlooked aspect is the impact on 3rd part vendors who supply application expertise to (the off shored developers). They are now redirecting their staff to other more stable accounts.

The IT industry does have a long memory and (the contract agency's and 3rd party vendors) will be loath to be engaged with Telstra as this debacle will be re-enacted next Christmas (2011).

Personally I am surprised Mr Thodey is in support of this cruel short noticed, prolonged lay-off of (used to be) dedicated Telstra IT contractors. I know that there is such a wave of bad feeling within the Telstra contracting community at their callous treatment - and the result will be a wave of contractors who will not return. This will have a major impact on already in-flight projects and a detrimental impact on Telstra's fragile bottom line and (to play on the Telstra jargon)decrease shareholder value. This is a shortsighted disgrace!!
jr22
Dec 5, 2010 10:44 PM
I'm sure all the shareholders out there would like to know that several projects that were scheduled to be delivered to large Telstra enterprise customers in the first half of 2011 will be affected by this. These clients are worth millions to Telstra and will feel the effects more than any retail customers.

Some of these projects have teams that are over 70% contractor resourced and will now run well over schedule. Not only does this delay these large customers' vital initiatives, but Telstra is also exposed to large financial penalties for not meeting promised dates. Think about where Telstra may attempt to regain those lost dollars for a moment.

Don't think that permanent staff can cover this shortfall either. There will be far too many links in the chain missing for any meaningful work to be completed.

Mr. Thodey, this is clearly nuts. This farcical attempt to save some pennies is going to cost your company and your shareholders millions of dollars and create a lot of ill will with some of your largest customers.

Let sanity prevail.
bitMissing
Dec 6, 2010 6:36 AM
Stop whingeing.
"...will show a short-term saving, where the real cost will not become apparent until the next financial year..."

It's not Telstra's fault.
This is what corporatisation and democracy is all about.
Look good, sweat off the guilt in the gym. End of story.
sydneyla
Dec 7, 2010 8:28 AM
I certainly do believe in fair treatment for all Telstra employees and the retention of employees who are an advantage to the company and certainly take the letter (unsigned) above seriously.

The fact is that gigantic changes will occur in the industry with the deployment of the optic fibre roll-out and Telstra management are duty bound to make changes that are necessary to ensure the survival of Telstra.
pameacs
Dec 8, 2010 9:29 AM
What I wonder is how this is written into the contracts and the only reason they get away with it is that they are the big guys and for the contractor to challenge if their action is not according to contract. Sometimes the organizations fully know the contractor wont challenge as they fear the long term effects of such a challenge. Losing everything as the court case drags out for years and years, only to be vindicated and get a settlement of $20,000 or something equally useless in the longer term isn't really a great option to the small guy. I guess as in all contracts that since one party has now opted to alter the terms, that the other party has an equal right to opt out of those altered terms.
Francis
Dec 12, 2010 5:55 AM
Frankly I am appalled at such action.
What Telstra has done may be within the letter of the law/contract for contractors but it is not in the best interest of Telstra, the Contractors concerned or the Consumer.
Employees be they contractors or otherwise have needs social and economic as well as feelings and emotions.
They are not inanimate objects such as a screwdriver which is thrown into a toolbox only to be removed when it is needed.
This form of employee relations, Contractor or otherwise is often counter productive. It also is poor public relations. I wonder how many people who are currently Telstra customers may change service providers due to this harsh action.
For maximum productivity employers and employees must have amenable instead of a confrontational relationship. While trapped in the middle are the consumers.

I hope my Telstra services do not break down during the shut down.
Finally it would serve Telstra right if the majority of these people found alternative employment during the shut down period and did not return leaving Telstra in a mess of their own creating.
This is nothing short of a loose loose situation for all parties.
Merry Xmas Mr Thodey
It's just a pity its at the expense of others.
marcusg
Dec 13, 2010 10:16 AM
The letter is well written, true and correct but it misses the point. Telstra is only interested in their shareholders. Anything that increases the profit, by slashing costs, management will do. This is despite earlier assurances that, under Mr Thodey, Telstra is all about the customer.

The NBN payout is also worth considering as it appears Mr. Thodey is hedging his bets by getting a payout via the government. It can only improve the overall bottom line. Staff, permanent or contract, are at the bottom of the heap.
Comments have been disabled for this article.
 
 
 
Top Stories
Australian miners send drones to work
In-depth: Unmanned aerial vehicles in the resources sector.
 
The New Zealand telco problem
Opinion: Could Telstra save Kiwi telcos?
 
IT price probe to 'name and shame' gougers
Industry ducking the issue, committee claims.
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

Latest Comments
Polls
Should the Government enact new legislation to protect copyright holders in the digital age?

   |   View results
Yes
  19%
 
No
  81%
TOTAL VOTES: 510

Vote