CERN is building a new data centre in Budapest, Hungary in an attempt to dramatically improve the compute resources available to particle physics experiments at the Large Hadron Collider (LHC).

The European organisation went to tender for a second 'Tier Zero' data centre after finding that its 1970s-era, 3.4 MW facility in Geneva, Switzerland was hitting capacity contraints.

It decided in May to build the new facility at the Wigner Research Centre for Physics in Budapest.

CERN operates the $6.3 billion LHC on the border of Switzerland and France, with a budget of about $164 million for IT equipment and labour over the life of the LHC's six experiments.

The experiments – including ATLAS and CMS, which famously announced the discovery of a "particle consistent with the Higgs Boson" last month – generate about one petabyte of data a second.

Of that, only about 700 megabits a second is committed to storage and/or processing at CERN’s on-site, 'Tier Zero' data centre.

The Tier Zero facility is the central hub of the Worldwide LHC Computing Grid, which also connects to some dozen ‘Tier One’ data centres for near-real time storage and analysis of data and over 150 ‘Tier Two’ data centres for batch analysis of experiment data.

Despite several decades of renovations and an ability to share resources across a globally distributed grid, Tier Zero in Geneva has in recent years been limited by the availability of power.

CERN’s activities use 230 MW of power, 120 MW of which is reserved specifically for the Large Hadron Collider. The CERN data centre uses 3.4 MW and is at full capacity.

“That means that essentially we can't put more equipment in there,” explained David Foster, deputy head of IT at CERN. “We are pushing more jobs to Tier One and Two data centres.”

Foster said CERN intended to "work towards doubling our capability" with the new Budapest facility, which would feature four computer rooms providing an additional 2.5 MW, with headroom to grow to about 5 MW.

This second Tier Zero facility will operate in lockstep with CERN’s Geneva data centre. From a technical perspective, the infrastructure deployed in it will be a logical extension of the existing architecture.

Wigner will manage the physical building, whilst the IT infrastructure deployed in the facility will be virtualised and managed remotely from the CERN’s Geneva control room.

All four rooms at the Hungary facility are expected to be complete by June 2013. The first of the rooms will be online by the end of this year.

Copyright © iTnews.com.au . All rights reserved.


 
 
 
 
Top Stories
Project management lessons from the QLD Health payroll inquiry
Analysis: How not to run a major IT project.
 
Review: Asus Fonepad
Calling on the Big Phone.
 
Photos: Highlights from SAP Sapphire Now 2013
All the keynote action from one of the world's biggest SAP events.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: ING Direct [The Benchmark Awards]
Judges notes: ING Direct [The Benchmark Awards]
iTnews' panel of judges discuss ING Direct's 'Bank in a Box', one of three shortlisted finalists for the banking and finance category of the CIO Benchmark Awards.
Judges notes: Yarra Valley Water [The Benchmark Awards]
Judges notes: Yarra Valley Water [The Benchmark Awards]
iTnews' panel of judges discuss Yarra Valley Water's insourcing project, one of three shortlisted finalists for the Utilities category of the CIO Benchmark Awards.
Latest Comments
Polls
Do you prefer the Coalition's NBN policy?

   |   View results
Yes
  19%
 
No
  81%
TOTAL VOTES: 1643

Vote