Defence mulls cloud models

 

Data centre scoping study reveals preference for 'physical private cloud'.

The Department of Defence has been advised to consider cloud computing as it moves to cut costs and rationalise its data processing environment.

In a newly released report "Initial Scoping Study of Defence Data Centre Service Delivery", PricewaterhouseCoopers consultants recommended that Defence opt for a "physical private cloud".

The report was provided to Defence in September 2010 to inform the department's Centralised Processing Project plans. It was issued to potential suppliers for the project this month.

Report authors recommended that Defence consolidate its central and regional services and data centres to support a more integrated enterprise services model.

This would reorient Defence to a more strategic IT “command and control” role, while integrators, service providers and other third parties managed various service delivery components under "more advantageous outsourcing contracts".

Citing case studies from its clients in the banking, telecommunications and resources sectors, PricewaterhouseCoopers expected Defence to opt for a private cloud that was custom-developed to meet the department's requirements of sovereignty, security, resilience, recoverability and survivability.

“This may be designed, built operated and maintained by the Cloud Enterprise Services Providers (CESPs). But may be specified, and owned by Defence,” authors noted.

While observing that cloud computing offered a “compelling value proposition”, report authors were concerned about the ownership of intellectual property and how clients might move off a cloud.

“What does the client own and what obligation does the CESP have to provide data and specifications enabling another cloud CESP to transform and load the data for residence within his cloud?" they wrote.

"The potential problem is untested but getting off a cloud may be difficult."

Why Defence is unable to deliver capacity on demand

Deficiencies in Defence’s current IT service delivery model seemed of even greater concern to the PricewaterhouseCoopers team.

Existing service level agreements and a lack of explicitly defined business-level outcomes had resulted in architecture, facilities and services that were "clearly not to Defence standards", the study found.

Report authors concluded that the current state of Defence's IT systems management could be “simply characterised by an inability to deliver capacity on demand”.

This was attributed to Defence’s project-orientated delivery model which failed to forecast resource needs or promote planning.

The study also highlighted differences in how central and regional services were delivered and an “inability to standardise and/or coordinate and manage these activities”.

The Defence Computing Bureau focused on delivering services centrally, while regions relied heavily on contracted service providers Unisys and Fujitsu.

Further, Defence’s monitoring tools were not integrated and their use was not standardised, the report found, warning that its Deakin Data Centre Migration (DCM) Project may consequently fail to realise consolidation objectives.

Single supplier to meet savings and service demand

PricewaterhouseCoopers expected Defence’s technology consumption to move from being asset-based to being services- or cloud-based.

Additionally, report authors said a significant amount of “workforce transformation” would be required to enable new business and ICT organisation structures to be implemented.

The report estimated total Defence centralised processing baseline costs for the nine-year period to FY2019/20 were estimated to be between $1.586 billion and $1.877 billion.

Based on PricewaterhouseCoopers' models, Defence may save between $180 million and $499 million by implementing PwC's centralised processing recommendations.

Defence was in the first of two procurement stages for its Centralised Processing Project.

It planned to shortlist up to six prime bidders by the second quarter of 2012 with a single prime being appointed by the second quarter of 2013 and the rollout to be completed by 2019.

Copyright © iTnews.com.au . All rights reserved.


Defence mulls cloud models
Sunlight through clouds
 
 
 
 
Top Stories
ATO commits to complexity
Greater demand, fewer apps.
 
Photos: AusCERT 2013 day two
The second day of the Queensland security conference.
 
The illusion of cognitive computing
Opinion: IBM's Watson is a marketing success.
 
 
Sunlight through clouds
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: ING Direct [The Benchmark Awards]
Judges notes: ING Direct [The Benchmark Awards]
iTnews' panel of judges discuss ING Direct's 'Bank in a Box', one of three shortlisted finalists for the banking and finance category of the CIO Benchmark Awards.
Judges notes: Yarra Valley Water [The Benchmark Awards]
Judges notes: Yarra Valley Water [The Benchmark Awards]
iTnews' panel of judges discuss Yarra Valley Water's insourcing project, one of three shortlisted finalists for the Utilities category of the CIO Benchmark Awards.
Latest Comments
Polls
Do you prefer the Coalition's NBN policy?

   |   View results
Yes
  19%
 
No
  81%
TOTAL VOTES: 1743

Vote