Exclusive: Inside Equinix's Sydney3 data centre

 

State-of-the-art facility opens for business.

View larger image View larger image View larger image

See all pictures here »

Equinix has started accepting the first customer equipment in stage one of its new Sydney3 (SY3) data centre.

The $77 million first stage was in "final commissioning" during iTnews' tour of the facility, with production power expected to be switched on to 1,000 racks this month.

Equinix Australia's managing director Darren Mann said the centre was "open for business", with the company taking orders from customers while "finishing touches" were added.

Stage one was under heat load testing when iTnews was provided exclusive access. The data centre operator had purchased approximately 3,000 fan heaters for the job.

Each of the three stages of construction would house two data halls that allowed for general co-location and private cages in a 30/70 split.

Plant in the data halls was colour-coded: grey for primary and orange for redundant infrastructure.

Among the plant used was Emerson Chloride Trinergy uninterruptible power supply (UPS) units, which Mann said offered Equinix "the highest efficiency for a double conversion UPS", and Trane chillers.

Equinix had installed a mix of centrifugal (high load) and low load chillers in the plant room. The centrifugal chiller with rapid restart offered high efficiency at full or part load operation, and was complimented by the low load chillers, Mann said.

Copyright © iTnews.com.au . All rights reserved.


 
 
 
Top Stories
Westpac committed to core banking plan
[Blog post] Now with leadership.
 
The True Cost of BYOD - 2014 survey
Twelve months on from our first study, is BYOD a better proposition?
 
Photos: Unboxing the Magnus supercomputer
Pawsey's biggest beast slots into place.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...
Latest Comments
Polls
What is delaying adoption of public cloud in your organisation?







   |   View results
Lock-in concerns
  30%
 
Application integration concerns
  3%
 
Security and compliance concerns
  27%
 
Unreliable network infrastructure
  9%
 
Data sovereignty concerns
  22%
 
Lack of stakeholder support
  3%
 
Protecting on-premise IT jobs
  4%
 
Difficulty transitioning CapEx budget into OpEx
  3%
TOTAL VOTES: 1170

Vote