Komatsu tests Telstra's disaster recovery skills

 
Page 1 of 2 | Single page

Runs all workloads on secondary site during Easter 'disaster'.

IT engineers from Komatsu and its managed hosting partners Telstra and Fujitsu spent the Easter and Anzac long weekend failing over the entire IT infrastructure of the industrial equipment giant to run at secondary facilities, in an exercise that tested Telstra's cloud credentials.

Komatsu is one of a small number of Australian corporations that has outsourced its entire IT infrastructure to Telstra’s IaaS service, branded ‘Network Computing Services’.

The company’s production x86 workloads (SAP, Microsoft Exchange and SharePoint, SQL, Navision and print and file, among others) run in a virtualised stack in Telstra’s Pitt Street data centre, with disaster recovery and data mirroring to the telco’s Melbourne facility.

Its mainframe workloads (a transactional system for its spares and services business) are co-located in the Sydney facility, with a secondary option at Fujitsu’s North Ryde facility waiting on standby.

Komatsu CIO Ian Harvison told iTnews today that one way to mitigate the risk of pushing all of its infrastructure to a third party was to run live disaster recovery exercises rather than mere simulations.

Harvison “declared” an emergency at 10pm on the Friday night of the Easter and Anzac long weekend.

Komatsu and Telstra's engineers then gave up their break to migrate Komatsu’s entire set of workloads to secondary facilities.

Komatsu set Telstra variable recovery point and recovery time objectives to meet. Applications that supported failover and load balancing would migrate instantaneously; a ‘B’ and ‘C’ group of applications (such as 14 Terabytes in SAP) had to be operational within 24 hours; and a ‘D, E and F’ group of applications (business systems such as email, file and print) would need to be migrated within a “best effort” timeframe.

The results were impressive – the SAP applications were operational in under four hours, the ‘C’ group in under an hour, the ‘D’ group in 45 minutes, ‘E’ in two hours and ‘F’ in four hours.

The only relative laggard was the company’s mainframe systems, which had to be rebuilt from the last tape back-up – a task that took 24 hours to complete.

Harvison said the test was ultimately very successful, with only three seconds of missing data and “no service degradation” beyond staff being unable to remote connect to systems.

The teams then ran the Melbourne (Telstra) and North Ryde (Fujitsu) secondary environments as production systems for two days.

“We have 24 x 7 agreements with customers like Rio Tinto – contracts that ensure we can get parts to their sites at any point in time,” he said.

“We literally ran transactions – part sales – for two days on our DR boxes.”

But Harvison didn’t want to stop there - the company also “failed back” onto its production systems in Sydney within the same weekend.

“We can say with our hands on our hearts that we can failover and run our organisation’s entire infrastructure in failure mode,” he said.

“It was Telstra’s first real test of failing over a customer on its cloud platform."

Read on for a discussion on why Komatsu chose to outsource its entire IT infrastructure...

Copyright © iTnews.com.au . All rights reserved.


Komatsu tests Telstra's disaster recovery skills
 
 
Comments: 0
Comments have been disabled for this article.
 
 
Top Stories
Review: Microsoft Surface Pro
A year is a long time in the computer hardware business.
 
 
NBN Co could miss revised June fibre targets
Analysis: Cutting it fine in the race to the line.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Vivek Kundra on Australia's 'cloud last' policy
Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Latest Comments
Polls
Will you quit any cloud services in light of PRISM?

   |   View results
Yes
  58%
 
No
  42%
TOTAL VOTES: 89

Vote