Photos: How to build a datacentre in 80 days

 

Half price racks on offer as new WA facility goes live.

View larger image View larger image View larger image

See all pictures here »

West Australian start-up HPC datacentres has built a functional, high-density co-lo centre capable of holding 120 racks in the Australian Marine Complex, just south of Perth.

The construction of the AMC data centre - shown in graphical detail in the gallery (top right) - saw HPC turn a concrete shell into an operational server room in just 80 days.

With a few redundancy features yet to be installed, the owner-operator has offered rack space at half price until September.

Design, cooling, connectivity

The AMC data centre features a raised floor and fake ceiling and offers to house customers' servers and networking equipment in Chatsworth cabinets.

Services will be sold per powered rack rather than per square metre, with the facility offering 12 kW per rack on average and up to 30 kW per rack on request. The base offering is 4 kW per rack.

HPC managing director Justin Thomas told iTnews that the young company could afford to chance new ideas from equipment vendors such as Chatsworth.

"We didn't have any pre-conceptions around using X or Y products," he said. "We didn't have that baggage, that comfort zone."

The cabinets are designed with a perforated front door, a solid back door and a chimney-like exhaust at the top, so that hot air from the rear of racks is separated from the cooler air at the front.

The hot air rises and is funnelled through the chimney into a plenum above the fake ceiling. From there, the hot air is pushed back into the cooling units and then, recirculated.

It's not hot aisle containment, since hot air never gets the chance to mix with the cold air, Thomas said.

"If I don't want to work in a thirty degree hot aisle, I wouldn't expect my staff too either," he said.

The facility is connected to fibre provided by both Telstra and Optus, plus a fibre link to a HPC point of presence within the Perth iX data centre, which interconnects with several national and international internet service providers and carriers.

AMC is fitted with Juniper EX4200 edge switches and SRX650 carrier-grade routers, with upgrades to MX series routers and EX8200 switches planned within six months.

In September, HPC also plans to introduce a microwave link, connecting the AMC data centre to facilities in the Perth CBD, as an additional layer of redundancy.

The facility uses Eaton Blade-Up UPS and Proniert gas for fire suppression.

Redundancy features on the way

Thomas told iTnews that rack space will be sold at half price at AMC until September to reflect "the lack of redundancy at this point."

A diesel generator is on order, and arrives in early September, as does the extra microwave link.

HPC is also planning to build a plant room adjacent to the facility.

At present, the data centre's UPS systems are located inside the server room and the main distribution board is sitting on the server room floor. But as more rack space is sold, HPC will finish off the plant room and move the plant equipment away from the racks.

Thomas said there would be no downtime during this transition.

"We are anticipating none," he said. "We have spent hours planning change management."

One key element to this modular approach is the use of Starline bus bars, manufactured by Universal Electric - which Thomas said was the same power distribution system used by Facebook, eBay and Sun Microsystems.

This system allows the data centre administrators to add or change power requirements "almost on the fly" without dropping power to a rack.

"The whole data centre is modular in design, you can plug and play and add and change infrastructure easily," Thomas said. "The facility is over-engineered for today, but ready for tomorrow."

Demand

Thomas expects the AMC's first customers to be those with one or two racks hosted elsewhere and wish to consolidate in a more modern, higher density facility.

He also expects demand from West Australian companies currently hosting with facilities on the East Coast. 

HPC eventually hopes to attract customers seeking 10-50 racks at a time, such that the company can start taking orders to build larger data centres.

The Australian Marine Complex is a large industrial with an adjoining technology precinct, which in itself could attract a number of customers for the data centre.

Thomas expects the AMC data centre to be the first of many data centres the company will construct.


"+1 In my mind it would be easy not to use the latest config because of lack of dollars in start-up mode."
By rycrozier
 
 
 
Comments: 2
Res
Jul 16, 2010 7:24 AM
"It's not hot aisle containment, since hot air never gets the chance to mix with the cold air, Thomas said."

I have used this approach myself, very efficient and has been the way of some DC's in the U.S. in recent times, and IMHO, is the way of the future, the less work the HVACs have to do, the better for your equipment, your own pocket and the environment.

Congratulations, well done.
rycrozier
Jul 16, 2010 8:34 AM
+1

In my mind it would be easy not to use the latest config because of lack of dollars in start-up mode.
Comments have been disabled for this article.
 
 
Top Stories
NBN Co could miss revised June fibre targets
Analysis: Cutting it fine in the race to the line.
 
Review: Sydney's Opal smartcard
It's no Oyster card.
 
Rackspace puts price premium on Aussie public cloud
At least 17 percent more compared to US instances.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Vivek Kundra on Australia's 'cloud last' policy
Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Latest Comments
Polls
Will you quit any cloud services in light of PRISM?

   |   View results
Yes
  67%
 
No
  33%
TOTAL VOTES: 57

Vote