Surges cut power to Centrelink data centre

 

Confirms cause of Easter weekend outage.

Centrelink has confirmed power surges at one its data centres in Canberra caused an emergency shutdown of the facility on the Easter long weekend.

The failure occurred just two months before the release of an Australian National Audit Office report, which exposed weaknesses in Centrelink's data centre and business continuity management procedures.

A spokesman for the agency told iTnews that IT services in the Canberra data centre were taken offline over the Easter weekend for "annual systems maintenance".

The centre is located at Tuggeranong in Canberra's south. Centrelink has a second facility in the Canberra suburb of Bruce and a separate data storage site.

The spokesman said maintenance work was completed and system health checks were being performed "when two power surges from the local grid damaged the uninterruptible power supply (UPS) infrastructure at the centre".

The result was that it did not failover to a back-up power source, causing an outage over the holiday weekend.

The surges led to an immediate shutdown of the centre, in line with the agency's emergency procedures, the spokesman said.

"Repairs were completed well before the system had to be back on-line for resumption of business Tuesday 14 April," he said.

"Subsequent maintenance has further strengthened the UPS arrays to avoid future issues. [But due to the timing], no customers, hardware, data or services were affected."

The Audit office [PDF] and Gershon [PDF] reports have cited Canberra's power grid as an ongoing risk to uptime in Federal Government data centre sites.

The Gershon report said "agencies [had] raised concerns over Canberra's reliance on a single power grid."

Canberra's grid has two feeds from NSW; one provides 85 percent of electricity to the Australian Capital Territory, and the second feed is only available in the outer suburb Fyshwick.

Centrelink hasn't been immune to power issues. The Audit office said it had previously experienced "a number of power outages to its data centres".

These included a December 2007 failure at the Bruce data centre that took services offline for 19 hours and a September 2006 event where primary and secondary systems at the same centre failed.

Centrelink also has other issues, the Audit office report found.

"There is no floor space available for future expansion, and relocation of the Tuggeranong data centre is considered urgent," the report stated.

"There are also air conditioning and other operational issues requiring urgent attention at both [Canberra data] centres."

The Audit office report found Centrelink's business continuity management framework and its implementation "lack the maturity that could be reasonably expected of Centrelink's size and complexity.

The framework is intended to limit or respond to disruptions to business disruptions that could impact the delivery of $70 billion in funds annually.

The Audit office called for improvements to high-level oversight and coordination of the framework and to business continuity planning and testing. Most planning activities still focused on crisis response, it said.

"Centrelink continues to work alongside other Government agencies to ensure the long-term integrity and security of its IT systems and data storage capability," a spokesman for the agency said.

Key points:
* Centrelink's Tuggeranong data centre loses power after twin surges on the Canberra electricity grid.
* The loss left customers and kit unaffected but underlines issues with the ACT grid network.
* UPS arrays have been upgraded to prevent a recurrence.


Surges cut power to Centrelink data centre
 
 
 
 
Top Stories
Review: Microsoft Surface Pro
A year is a long time in the computer hardware business.
 
 
NBN Co could miss revised June fibre targets
Analysis: Cutting it fine in the race to the line.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Vivek Kundra on Australia's 'cloud last' policy
Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Latest Comments
Polls
Will you quit any cloud services in light of PRISM?

   |   View results
Yes
  59%
 
No
  41%
TOTAL VOTES: 93

Vote