Inside the manageNET ASIO T4 data centre

 
Page 1 of 2 | Single page

iTnews takes a look at how the old Baltimore Technologies data centre in northern Sydney is getting a new lease on life.

View larger image View larger image View larger image

See all pictures here »

manageNET is planning the first major refresh of its managed services and colo data centre since acquiring the facility in 2005, with new racks, overhead cabling and hot/cold aisle containment solutions all potentially on the cards.

The company runs the 190 square metre data centre in a typically non-descript building on Sydney’s lower north shore (see photos right).

It was originally built by Baltimore Technologies back in 2000 and underwent a series of tenancy changes before manageNET took hold of it in 2005.

“We bought the site as it was,” said Con Dalamangas, chief technical officer of manageNET.

“It was built in 2000 with best practices [at the time]. We didn’t have to touch anything.”

After some four years at the site, however, manageNET is looking to make its first changes.

“You’ve always got to be looking at how you can refresh,” said James Baker, a senior network engineer at manageNET.

“We’re looking at things like hot/cold aisles and how we can extend the life of the data centre from a cooling perspective.

“The equipment isn’t contained in any way at this point but we know that small changes could make a big difference to the centre’s heat load and capacity,” said Baker.

The centre runs on a typical raised floor; cool air is directed through vents located in front of the racks and drawn though perforated doors to the equipment.

Cabling is also under-floor, although this could feasibly change as part of the refresh cycle, according to Baker.

“There’s a false ceiling but we’re not running anything overhead at the moment,” said Baker.

“All services run under the floor but that will likely change as we move to new rack designs.”

Apart from efficiency, one of the reasons manageNET is looking to refresh is to free up floor space and prolong the life of the centre.

“We’ve got limited floor space that we have to use intelligently,” said Baker.

“Virtualisation and blade architectures could help us get more out of that. Some of the new blade servers from Dell are interesting but they came out after we committed [to our current architecture].”

For the most part, manageNET has standardised on Dell PowerEdge 1950 servers ‘maxed out with 32GB of memory’. Blades were considered at the beginning but technical and pricing issues made them unsuitable.

“The blade options we looked at back then either didn’t have the right port density or were so expensive that it blew the idea out of the water,” explained Baker.

On the physical side, the centre runs dual Liebert CRACs in an N+1 redundant configuration, Chloride UPS, a VESDA fire system, and a near-new Petbow diesel-powered generator.

“The gen kicked in for the first time during a major blackout a couple of months ago,” said Baker.

“We do monthly start-ups on it and keep refueling it on-the-fly.”

The data centre has a network operations centre (NOC) onsite as well as office space that is currently let to some of its managed services clients.


 
 
 
 
Top Stories
Review: Microsoft Surface Pro
A year is a long time in the computer hardware business.
 
 
NBN Co could miss revised June fibre targets
Analysis: Cutting it fine in the race to the line.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Vivek Kundra on Australia's 'cloud last' policy
Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Latest Comments
Polls
Will you quit any cloud services in light of PRISM?

   |   View results
Yes
  59%
 
No
  41%
TOTAL VOTES: 86

Vote