A rare and exclusive look at the results of the last phase of construction and power and cooling upgrades at one of the region’s flagship data centres.
on Apr 6 2009 11:46AM
Front desk security. Two security guards are on duty 24x7.
Central floor corridor with data suites off each side. The facility has 7 floors of data suites.
Access way for one of the 1,500 m2 data suites.
Dedicated Staging and Storage Space - First look inside one of the new pre-production/test rooms. These are a new offering by Globalswitch.
33 kV/11 kV transformer. Global Switch has two in an N+1 configuration.
Part of the N+N INERGEN® gas fire suppression system.
Trane 4.5 MW Chiller. 7 in total in N+1 configuration.
Cooling Towers supporting the Chillers. There are 21 in total.
Close up of Cooling Towers.
Piller Rotary UPS Systems (22 in total).
UPS and their paired 2.2 MVA generators are grouped into power centres of three pairs. The facility has six power centres plus a redundant bank of four pairs.
Sound proofing between the UPS and external walls of the building, as viewed from beside the UPS.
Sound-proofing close-up - check out the thickness of the structure. Of course, Pyrmont is now a high-rise residential area, too...
View from the roof top looking South East.
Front desk security. Two security guards are on duty 24x7.