Telstra, NBN Co spar over conduit drawings

By Ry Crozier
Oct 13 2011 9:34AM
Follow google news

Ownership stoush rears ugly head again.

Telstra has reignited a stalemate with NBN Co over conduit ownership that is stalling the rollout of NBN fibre in up to 60 new housing estates across Australia.

Telstra, NBN Co spar over conduit drawings

The telco is allegedly refusing to hand over crucial drawings of the conduits it has been commissioned to lay in some new estates.

NBN Co requires the ownership rights to pit-and-pipe infrastructure before it will agree to roll out fibre under obligations it assumed from the beginning of this year.

Access to the "as-built" or "as-constructed" drawings of the laid conduits are required as part of the handover.

Developers that commissioned and paid Telstra to design and deploy the NBN-ready conduits are in limbo, according to Robin Russell & Associates managing director Robin Russell.

"There's three or four estates of ours where Telstra have sent documents to say they'll give ownership [of the conduits to NBN Co] but then they won't supply AutoCAD drawings as constructed and NBN Co says we can't do anything without AutoCAD drawings," Russell said.

"No one wants to solve the problems. People are going to be in their houses waiting for months for telephones."

An NBN Co spokesman confirmed the issue but said it was willing to accept the conduit drawings in any format.

"NBN Co does need to have the as-built drawings to complete the network design," the spokesman said.

"We have said we will take them in a range of formats, so we are not relying on the AutoCADs.

"We are working with Telstra to gain access to the drawings as quickly as possible."

A Telstra spokesman declined to comment directly on whether the as-constructed drawings are freely available to NBN Co, or what roadblocks are preventing it from handing over the data.

"The transfer of files and information between Telstra and NBN Co is the subject of confidential arrangements between the parties," Telstra's spokesman said.

The recurrence of conduit ownership issues raised questions about the status of a June policy statement by the Federal Government designed to resolve the tussle, which had first surfaced in April this year.

Allegations of Telstra withholding the crucial drawings come as a blow to that agreement.

A spokesman for the Department of Broadband, Communications and the Digital Economy (DBCDE) did not return a request for comment on the status of the policy document.

But Telstra said it remained "committed" to the policy and its obligations.

"Under the policy statement, developers are responsible for the installation of fibre-ready pit-and-pipe," the telco's spokesman said.

"The statement also deals with requirements on the developer to transfer ownership in the pit-and-pipe to NBN Co or Telstra.

"Telstra is following the policy statement and will agree to transfer ownership of pit-and-pipe in accordance with that statement."

Telstra said it would only refuse to transfer ownership of pit-and-pipe where it had paid for the infrastructure or where the developer still owed it money.

Add iTnews as your trusted source

Add iTnews As Your Trusted Source Add iTnews As Your Trusted Source
Got a news tip for our journalists? Share it with us anonymously here.
Copyright © iTnews.com.au . All rights reserved.
Tags:
conduitestatesgreenfieldgreenfieldshousingnbnconewownershippassivepipepittelco/isptelecommunicationstelstra

Related Articles

  • Superloop self-serve AI resolutions top 330,000 cases Superloop self-serve AI resolutions top 330,000 cases
  • Superloop merges wholesale FTTP operations under a single brand Superloop merges wholesale FTTP operations under a single brand
  • TPG Telecom using AI to chase better customer NPS TPG Telecom using AI to chase better customer NPS
  • Telstra, Google Cloud take capacity on each other's networks Telstra, Google Cloud take capacity on each other's networks
Join our WhatsApp Channel

Partner Content

Why resilient communications are becoming critical infrastructure for modern enterprise IT
Promoted Content Why resilient communications are becoming critical infrastructure for modern enterprise IT
CommBank creates opportunities for technologists to upskill  with frontier AI companies
Partner Content CommBank creates opportunities for technologists to upskill with frontier AI companies
Take control of your connectivity with Telstra’s Adaptive Networks Centre
Partner Content Take control of your connectivity with Telstra’s Adaptive Networks Centre
Intelligence × Trust: the equation that will decide Australia's AI winners
Promoted Content Intelligence × Trust: the equation that will decide Australia's AI winners

Sponsored Whitepapers

Agile in the AI Era: why projects still fail
Agile in the AI Era: why projects still fail
When Technology Becomes the Blocker: Unlocking Real Outcomes from AI and Cloud
When Technology Becomes the Blocker: Unlocking Real Outcomes from AI and Cloud
High-volume data sources for AI-driven security analytics
High-volume data sources for AI-driven security analytics
How healthcare organisations can get more value from cloud
How healthcare organisations can get more value from cloud
1 in 3 companies lose SaaS data. Here’s how to prevent it
1 in 3 companies lose SaaS data. Here’s how to prevent it

Events

  • iTnews State of Security Breakfast iTnews State of Security Breakfast
  • iTnews State of Data & AI Breakfast iTnews State of Data & AI Breakfast
  • The 2026 iAwards The 2026 iAwards
  • Integrate 2026 Integrate 2026
  • Security Exhibition & Conference Security Exhibition & Conference
Share on Facebook Share on LinkedIn Share on Whatsapp Email A Friend

Most Read Articles

Telstra elevates Dayle Stevens to company-wide AI role

Telstra elevates Dayle Stevens to company-wide AI role

Superloop merges wholesale FTTP operations under a single brand

Superloop merges wholesale FTTP operations under a single brand

TPG Telecom using AI to chase better customer NPS

TPG Telecom using AI to chase better customer NPS

Superloop self-serve AI resolutions top 330,000 cases

Superloop self-serve AI resolutions top 330,000 cases

techpartner.news logo
Sydney-based AI-cloud waste startup raises $3m
Sydney-based AI-cloud waste startup raises $3m
Brennan uses NiCE to modernise its contact centre
Brennan uses NiCE to modernise its contact centre
Impact Awards: Tecala slashes customer response times for fintech IQumulate
Impact Awards: Tecala slashes customer response times for fintech IQumulate
Interactive introduces private cloud platform
Interactive introduces private cloud platform
Digital61 expands cybersecurity portfolio
Digital61 expands cybersecurity portfolio
All rights reserved. This material may not be published, broadcast, rewritten or redistributed in any form without prior authorisation.
Your use of this website constitutes acceptance of nextmedia's Privacy Policy and Terms & Conditions.