NBN Co reveals 58 percent of HFC network still unserviceable

By Ry Crozier on Dec 13, 2018 12:16PM
NBN Co reveals 58 percent of HFC network still unserviceable

Almost 1.2m premises can’t support a retail service.

NBN Co has revealed that 58 percent of its hybrid fibre coaxial (HFC) footprint remains unserviceable, seven months after the sales freeze on connections was lifted.

The network builder said that as of November 16 there were still 1,192,965 premises in the HFC footprint whose connections were classed as unserviceable.

That equated to 58.2 percent of all HFC premises declared ready for service, the company said.

“The HFC figure is temporarily inflated during the period of the activations pause,” NBN Co said in notes accompanying the 58 percent figure, repeating verbatim a statement it previously made back in April.

“The majority of premises in the ‘paused’ HFC footprint will be moved to other serviceable classes throughout 2018 and a corresponding fall in the HFC percentage can be expected.”

NBN Co froze HFC sales between December 11 last year and late April this year so it could remediate parts of the network and improve performance. It kept rolling out more HFC despite not being able to sell any.

That meant that, by July, the sales freeze had impacted about 1.38 million HFC premises.

As per NBN Co’s statement, the number of unserviceable HFC premises was meant to reduce fairly quickly through the back half of this year.

“From July onwards NBN Co expects to significantly ramp up the release of HFC premises to retailers, forecast to hit around 100,000 premises per month,” the company said back in April.

It remains unclear how close to this pace of re-release that NBN Co has gotten. 

iTnews understands that NBN Co has remediated and released around 700,000 premises originally caught up in the freeze, which would put it close to the 100,000 premises a month release target.

An NBN Co spokesperson told iTnews that "NBN Co has been taking a conservative approach, as we will not prioritise build and activation progress at the expense of customer experience.

"We're releasing limited premises back for resale to ensure we have fully optimised and improved HFC connections on the NBN access network.”

What is clear is that the 58 percent of HFC unserviceable figure is far higher than it was even in March this year - at the height of the sales freeze.

At that time, NBN Co reported that 35.5 percent of all HFC connections were unserviceable.

HFC now also completely dominates the total number of unserviceable premises in the entire NBN rollout.

In September last year, HFC lines accounted for 53.7 percent of all lines in limbo. As of November 16 this year, 89.7 percent of all unserviceable connections on the NBN were HFC.

Updated at 4.30pm with comments from NBN Co.

Got a news tip for our journalists? Share it with us anonymously here.
Copyright © iTnews.com.au . All rights reserved.
Tags:
connection hfc line nbn nbn co sc0 telco/isp unserviceable

Partner Content

As Australian companies lean more heavily on the cloud, edge security is finding its stride
Partner Content As Australian companies lean more heavily on the cloud, edge security is finding its stride
Resetting cyber security for the new threat landscape
Partner Content Resetting cyber security for the new threat landscape
Four data superpowers to harness before 2022
Promoted Content Four data superpowers to harness before 2022
Beat the DDoS blackmails in 2021
Promoted Content Beat the DDoS blackmails in 2021

Sponsored Whitepapers

The top 5 tech trends to deliver business outcomes
The top 5 tech trends to deliver business outcomes
10 reasons why businesses need to invest in cloud security training
10 reasons why businesses need to invest in cloud security training
Your guide to application security solutions
Your guide to application security solutions
State of Software Security: Open Source Edition
State of Software Security: Open Source Edition
Five questions to ask before you upgrade to a SIEM solution
Five questions to ask before you upgrade to a SIEM solution

Events

  • On-Demand Webinar: How Poly and Microsoft are Embracing Future Work Environments
  • [iTnews and Micro Focus] Navigating the cloud modernisation minefield
By Ry Crozier
Dec 13 2018
12:16PM
0 Comments

Related Articles

  • NBN Co to resume new HFC orders from May
  • NBN Co to stop taking new HFC orders for 'several months'
  • Telstra's free NBN speed boost backfires
  • NBN Co is skipping "thousands" of premises a month
Share on Twitter Share on Facebook Share on LinkedIn Share on Whatsapp Email A Friend

Most Read Articles

TPG Telecom to start enticing NBN customers to move

TPG Telecom to start enticing NBN customers to move

Infosys scores another $40m for Centrelink payments engine build

Infosys scores another $40m for Centrelink payments engine build

Telstra InfraCo opens up telco's own fibre network

Telstra InfraCo opens up telco's own fibre network

Transport for NSW data stolen in Accellion breach

Transport for NSW data stolen in Accellion breach

You must be a registered member of iTnews to post a comment.
Log In | Register
All rights reserved. This material may not be published, broadcast, rewritten or redistributed in any form without prior authorisation.
Your use of this website constitutes acceptance of nextmedia's Privacy Policy and Terms & Conditions.