SP AusNet Vic smart meter rollout delayed indefinitely

By Allie Coyne on May 15, 2014 4:51PM
SP AusNet Vic smart meter rollout delayed indefinitely

AMI systems struggling under load.

The rollout of 714,000 smart meters in Victoria by power distributor SP AusNet has once again been set back after the company hit issues dealing with the increased load on its metering systems.

The Victorian government mandated the installation of smart meters in every household and small business across the state in 2006. Existing meter replacement started in 2009 and was to be completed by the end of 2013.

SP AusNet, alongside the state’s four other electricity distribution providers, is responsible for the rollout.

The company last year indicated its portion of the rollout, which was initially scheduled for completion by the end of 2013, would take six months longer than planned.

In its full year 2014 results released today the power distributor revealed it has been forced to push back its June 2014 deadline as well, as a result of issues with its advanced metering infrastructure (AMI) systems.

The AMI system facilitates automated communication between the smart meter and the utility company, in order to provide data to both the company and the customer about energy usage.

SP AusNet has installed 686,000 smart meters so far, but only 390,000 have been converted to run on the AMI systems.

The systems are struggling to deal with the increase in connected smart meters, resulting in periods of “significant instability” across the systems, SP AusNet said in its financial filings.

It told shareholders it was conducting a technical review of the IT to address the problem. 

“SP AusNet will now undertake further work to determine options and risks to its program to convert the remaining smart meters and to ensure that its AMI systems will be able to deliver the mandated performance consistently at this scale,” it told investors.

The company indicated that additional investment will be required to fix the issue, the value of which is “currently under review”.

It said it would pursue regulatory avenues to recover the additional expenditure, which would be subject to the approval of the Australian Energy Regulator.

Given the ongoing review of the AMI systems, it was not able to provide a completion date or cost for the rollout.

In addition, SP AusNet is struggling against customer refusals and inaccessible sites as it works to get the remaining 27,000 smart meters installed.

It is “proactively managing” both challenges, the company said.

Got a news tip for our journalists? Share it with us anonymously here.
Copyright © iTnews.com.au . All rights reserved.
Tags:
electricityenergymeternetworkingpowersmart metersp ausnetusagevictoria

Partner Content

How to turn digital complexity into competitive advantage
Promoted Content How to turn digital complexity into competitive advantage
Why Genworth Australia embraced low-code software development
Promoted Content Why Genworth Australia embraced low-code software development
The Great Resignation has intensified insider security threats
Promoted Content The Great Resignation has intensified insider security threats
Accenture and Google Cloud team up to create a loveable, Australian-first, renewable energy product
Promoted Content Accenture and Google Cloud team up to create a loveable, Australian-first, renewable energy product

Sponsored Whitepapers

Extracting the value of data using Unified Observability
Extracting the value of data using Unified Observability
Planning before the breach: You can’t protect what you can’t see
Planning before the breach: You can’t protect what you can’t see
Beyond FTP: Securing and Managing File Transfers
Beyond FTP: Securing and Managing File Transfers
NextGen Security Operations: A Roadmap for the Future
NextGen Security Operations: A Roadmap for the Future
Video: Watch Juniper talk about its Aston Martin partnership
Video: Watch Juniper talk about its Aston Martin partnership

Events

  • Micro Focus Information Management & Governance (IM&G) Forum 2022
  • CRN Channel Meets: CyberSecurity Live Event
  • IoT Insights: Secure By Design for manufacturing
  • Cyber Security for Government Summit
By Allie Coyne
May 15 2014
4:51PM
0 Comments

Related Articles

  • CS Energy CIO Terry Melton departs
  • WA trials Telstra tower on off-grid power
  • Telstra, Intellihub in $100 million energy connectivity deal
  • Victoria enlists Section for whole-of-gov website delivery
Share on Twitter Share on Facebook Share on LinkedIn Share on Whatsapp Email A Friend

Most Read Articles

Qantas calls time on IBM, Fujitsu in tech modernisation

Qantas calls time on IBM, Fujitsu in tech modernisation

Service NSW hits digital services goal two years early

Service NSW hits digital services goal two years early

NBN Co taking orders for 'non-premises' connections

NBN Co taking orders for 'non-premises' connections

NSW Police scores $100m to connect body-cams to firearms, tasers

NSW Police scores $100m to connect body-cams to firearms, tasers

Digital Nation

IBM global chief data officer on the rise of the number crunchers
IBM global chief data officer on the rise of the number crunchers
Crypto experts optimistic about future of Bitcoin: Block
Crypto experts optimistic about future of Bitcoin: Block
COVER STORY: Operationalising net zero through the power of IoT
COVER STORY: Operationalising net zero through the power of IoT
Integrity, ethics and board decisions in the digital age
Integrity, ethics and board decisions in the digital age
The security threat of quantum computing
The security threat of quantum computing
All rights reserved. This material may not be published, broadcast, rewritten or redistributed in any form without prior authorisation.
Your use of this website constitutes acceptance of nextmedia's Privacy Policy and Terms & Conditions.