NBN Co revises greenfields rollout process

By James Hutchinson
Feb 16 2012 11:28AM
Follow google news

Residents in NBN limbo to get interim Telstra service.

NBN Co has revised its fibre installation process in new housing estates in a bid to address delays in connecting homes to the National Broadband Network.

NBN Co revises greenfields rollout process

The network wholesaler, which acts as fibre provider "of last resort" in developments of more than 100 homes, has begun installing customer equipment in homes before connecting homes to the network or provisioning backhaul.

It hopes to solve delays of as much as six months in activating NBN services for some residents in new housing estates.

Industry sources told iTnews that the delays had caused some developers to opt for a rival fibre installer rather than the Government-subsidised option in order to get the work done in time.

An NBN Co spokeswoman confirmed "around 100 premises" had been affected by the delays, meaning residents had moved into new homes without an active telephone or internet connection.

Some users on telco user forum Whirlpool recounted difficulty in activating an NBN service in situations where they had moved into a new home ahead of the official go live date for connections in that development.

Remember to sign up to our new Telecommunications bulletin to stay connected with a concise online wrap of Australiaís telecommunications and ISP industry.

NBN Co CEO Mike Quigley acknowledged the problem this week, attributing delays in provisioning backhaul to a lack of duct infrastructure in new regional or outer-metropolitan developments, requiring additional installation by NBN Co.

"Fibre builds in excess of six kilometres for each of these estates are the norm now," he told a Senate estimates hearing this week.

"Taking on the wholesale universal service obligation for these estates before we have a network is obviously not easy so it's no surprise it's taking some time.

"We're working hard to meet the demand of developers and solve this timing problem - we're confident that we will."

He said Telstra would likely be asked to provide "interim telephone services" in new developments where delays had occurred in new developments.

An NBN Co spokeswoman could not clarify how many of the 100 premises affected have applied for such a service.

Telstra confirmed some services had been provied to residents waiting on NBN connections but would not clarify how many or what technology was used.

It is believed any such service is likely to be provided off its Next G network rather than new copper or fibre lines in new developments.

NBN Co's revised process would allow new homes to be "activated when the network is operational".

But correspondence between NBN Co and greenfield developers, sighted by iTnews, show the wholesaler could not guarantee a "standard delivery timeframe" for network connections in new developments, due to the time differences in connecting a greenfield estate to backhaul around Australia.

NBN Co has planned to roll out fibre in 264 new developments so far this year, covering nearly 13,000 premises.

Add iTnews as your trusted source

Add iTnews As Your Trusted Source Add iTnews As Your Trusted Source
Got a news tip for our journalists? Share it with us anonymously here.
Copyright © iTnews.com.au . All rights reserved.
Tags:
broadbandgreenfieldsnational broadband networknbnnbn cotelco/isptelecommunications

Related Articles

  • Superloop self-serve AI resolutions top 330,000 cases Superloop self-serve AI resolutions top 330,000 cases
  • Superloop merges wholesale FTTP operations under a single brand Superloop merges wholesale FTTP operations under a single brand
  • TPG Telecom using AI to chase better customer NPS TPG Telecom using AI to chase better customer NPS
  • Telstra, Google Cloud take capacity on each other's networks Telstra, Google Cloud take capacity on each other's networks
Join our WhatsApp Channel

Partner Content

Why resilient communications are becoming critical infrastructure for modern enterprise IT
Promoted Content Why resilient communications are becoming critical infrastructure for modern enterprise IT
Agile isn’t the problem: why projects still fail, and what’s missing
Partner Content Agile isn’t the problem: why projects still fail, and what’s missing
AI is delivering business value today
Partner Content AI is delivering business value today
You meet the security standard. Shame no one can see it
Promoted Content You meet the security standard. Shame no one can see it

Sponsored Whitepapers

Agile in the AI Era: why projects still fail
Agile in the AI Era: why projects still fail
When Technology Becomes the Blocker: Unlocking Real Outcomes from AI and Cloud
When Technology Becomes the Blocker: Unlocking Real Outcomes from AI and Cloud
High-volume data sources for AI-driven security analytics
High-volume data sources for AI-driven security analytics
How healthcare organisations can get more value from cloud
How healthcare organisations can get more value from cloud
1 in 3 companies lose SaaS data. Here’s how to prevent it
1 in 3 companies lose SaaS data. Here’s how to prevent it

Events

  • iTnews State of Security Breakfast iTnews State of Security Breakfast
  • iTnews State of Data & AI Breakfast iTnews State of Data & AI Breakfast
  • The 2026 iAwards The 2026 iAwards
  • Integrate 2026 Integrate 2026
  • Security Exhibition & Conference Security Exhibition & Conference
Share on Facebook Share on LinkedIn Share on Whatsapp Email A Friend

Most Read Articles

Telstra elevates Dayle Stevens to company-wide AI role

Telstra elevates Dayle Stevens to company-wide AI role

Superloop merges wholesale FTTP operations under a single brand

Superloop merges wholesale FTTP operations under a single brand

TPG Telecom using AI to chase better customer NPS

TPG Telecom using AI to chase better customer NPS

SUBCO, Firmus to double Tasmania's undersea internet capacity to mainland

SUBCO, Firmus to double Tasmania's undersea internet capacity to mainland

techpartner.news logo
Sydney-based AI-cloud waste startup raises $3m
Sydney-based AI-cloud waste startup raises $3m
Brennan uses NiCE to modernise its contact centre
Brennan uses NiCE to modernise its contact centre
Impact Awards: Tecala slashes customer response times for fintech IQumulate
Impact Awards: Tecala slashes customer response times for fintech IQumulate
Interactive introduces private cloud platform
Interactive introduces private cloud platform
Digital61 expands cybersecurity portfolio
Digital61 expands cybersecurity portfolio
All rights reserved. This material may not be published, broadcast, rewritten or redistributed in any form without prior authorisation.
Your use of this website constitutes acceptance of nextmedia's Privacy Policy and Terms & Conditions.