iTnews takes a look at how the old Baltimore Technologies data centre in northern Sydney is getting a new lease on life.

manageNET is planning the first major refresh of its managed services and colo data centre since acquiring the facility in 2005, with new racks, overhead cabling and hot/cold aisle containment solutions all potentially on the cards.

The company runs the 190 square metre data centre in a typically non-descript building on Sydney’s lower north shore (see photos right).

It was originally built by Baltimore Technologies back in 2000 and underwent a series of tenancy changes before manageNET took hold of it in 2005.

“We bought the site as it was,” said Con Dalamangas, chief technical officer of manageNET.

“It was built in 2000 with best practices [at the time]. We didn’t have to touch anything.”

After some four years at the site, however, manageNET is looking to make its first changes.

“You’ve always got to be looking at how you can refresh,” said James Baker, a senior network engineer at manageNET.

“We’re looking at things like hot/cold aisles and how we can extend the life of the data centre from a cooling perspective.

“The equipment isn’t contained in any way at this point but we know that small changes could make a big difference to the centre’s heat load and capacity,” said Baker.

The centre runs on a typical raised floor; cool air is directed through vents located in front of the racks and drawn though perforated doors to the equipment.

Cabling is also under-floor, although this could feasibly change as part of the refresh cycle, according to Baker.

“There’s a false ceiling but we’re not running anything overhead at the moment,” said Baker.

“All services run under the floor but that will likely change as we move to new rack designs.”

Apart from efficiency, one of the reasons manageNET is looking to refresh is to free up floor space and prolong the life of the centre.

“We’ve got limited floor space that we have to use intelligently,” said Baker.

“Virtualisation and blade architectures could help us get more out of that. Some of the new blade servers from Dell are interesting but they came out after we committed [to our current architecture].”

For the most part, manageNET has standardised on Dell PowerEdge 1950 servers ‘maxed out with 32GB of memory’. Blades were considered at the beginning but technical and pricing issues made them unsuitable.

“The blade options we looked at back then either didn’t have the right port density or were so expensive that it blew the idea out of the water,” explained Baker.

On the physical side, the centre runs dual Liebert CRACs in an N+1 redundant configuration, Chloride UPS, a VESDA fire system, and a near-new Petbow diesel-powered generator.

“The gen kicked in for the first time during a major blackout a couple of months ago,” said Baker.

“We do monthly start-ups on it and keep refueling it on-the-fly.”

The data centre has a network operations centre (NOC) onsite as well as office space that is currently let to some of its managed services clients.

Inside the manageNET ASIO T4 data centre
Linked gallery: Inside the manageNET ASIO T4 data centre
High-tech security

The data centre was one of the first to gain ASIO T4 security status in Australia – a certification that manageNET has maintained for both the centre and its operations staff.

Security status has helped them win some big deals, according to Dalamangas.

“We’ve all passed ASVS background checks and the centre has Highly Protected status,” said Dalamangas.

“In 2007, that allowed us to win a contract with Thales Australia around the APEC Summit. They were looking for a T4 site in NSW as part of a year-long colocation and managed security services engagement, and we bid successfully for that piece of work.

He continued: “We have three suites within the data centre that are also T4 certified. They’re good for customers who like privacy or want to run specific application hosting requirements.”

One of the reasons the centre was built to the ASIO T4 standard in the first place is because it originally housed some of the public key infrastructure (PKI) equipment behind early iterations of the Federal Government’s Gatekeeper framework.

The framework was designed to make PKI less complex and more cost effective for businesses and government agencies.

“The site was used as part of a blueprint for the Gatekeeper standard,” said Dalamangas.

In fact, the centre has always maintained ties with the IT security sector. It was previously also owned by Betrusted.

The data centre’s high security background was a perfect fit for manageNET. When it formed back in 2003, it focused on managed security services, such as firewall and unified threat management, using technologies from the likes of Fortinet and Sonicwall.

The company has since expanded into other areas from a data centre perspective, notably PCI DSS compliant hosting, a selected colo offering and a virtual hosted platform. The latter is built with VMware ESX running on Dell servers and storage, Nortel switches and an Overland tape library.

“ASIO T4 is primarily about physical security,” said Dalamangas.

“We also have security enshrined in the procedural and technology aspects of the data centre, such as sign-in and escorting of customers and third parties within the facility, iris and biometric scanners on entry doors, magnetic locks, electronic surveillance and laser detection, and equipment protection.

Add iTnews as your trusted source

Add iTnews As Your Trusted Source Add iTnews As Your Trusted Source
Next Page 1 2 Single page
Got a news tip for our journalists? Share it with us anonymously here.
Tags:
asiocentredataefficiencyhardwareinsidedcnetworkingpowerrackssecurity

Related Articles

  • Microsoft teases new era of AI-driven devices Microsoft teases new era of AI-driven devices
  • PsiQuantum to build computer at Moreton Bay PsiQuantum to build computer at Moreton Bay
  • US to invest in IBM, other quantum computing firms US to invest in IBM, other quantum computing firms
  • South Korea says it will pursue all options to avoid Samsung strike South Korea says it will pursue all options to avoid Samsung strike
Join our WhatsApp Channel

Partner Content

You meet the security standard. Shame no one can see it
Promoted Content You meet the security standard. Shame no one can see it
From test case to control tower: How DXC and ServiceNow are governing enterprise AI at scale
Promoted Content From test case to control tower: How DXC and ServiceNow are governing enterprise AI at scale
Intelligence × Trust: the equation that will decide Australia's AI winners
Promoted Content Intelligence × Trust: the equation that will decide Australia's AI winners
Why resilient communications are becoming critical infrastructure for modern enterprise IT
Promoted Content Why resilient communications are becoming critical infrastructure for modern enterprise IT

Sponsored Whitepapers

Agile in the AI Era: why projects still fail
Agile in the AI Era: why projects still fail
When Technology Becomes the Blocker: Unlocking Real Outcomes from AI and Cloud
When Technology Becomes the Blocker: Unlocking Real Outcomes from AI and Cloud
High-volume data sources for AI-driven security analytics
High-volume data sources for AI-driven security analytics
How healthcare organisations can get more value from cloud
How healthcare organisations can get more value from cloud
1 in 3 companies lose SaaS data. Here’s how to prevent it
1 in 3 companies lose SaaS data. Here’s how to prevent it

Events

  • iTnews State of Security Breakfast iTnews State of Security Breakfast
  • iTnews State of Data & AI Breakfast iTnews State of Data & AI Breakfast
  • The 2026 iAwards The 2026 iAwards
  • Integrate 2026 Integrate 2026
  • Security Exhibition & Conference Security Exhibition & Conference
Share on Facebook Share on LinkedIn Share on Whatsapp Email A Friend

Most Read Articles

Google says it has cracked a quantum computing challenge

Google says it has cracked a quantum computing challenge

Microsoft teases new era of AI-driven devices

Microsoft teases new era of AI-driven devices

Australian teen leaks pictures of new iPhone parts

Australian teen leaks pictures of new iPhone parts

Federal Court orders Google to pay $55 million for anti-competitive conduct

Federal Court orders Google to pay $55 million for anti-competitive conduct

techpartner.news logo
Sydney-based AI-cloud waste startup raises $3m
Sydney-based AI-cloud waste startup raises $3m
Brennan uses NiCE to modernise its contact centre
Brennan uses NiCE to modernise its contact centre
Impact Awards: Tecala slashes customer response times for fintech IQumulate
Impact Awards: Tecala slashes customer response times for fintech IQumulate
Interactive introduces private cloud platform
Interactive introduces private cloud platform
Digital61 expands cybersecurity portfolio
Digital61 expands cybersecurity portfolio
All rights reserved. This material may not be published, broadcast, rewritten or redistributed in any form without prior authorisation.
Your use of this website constitutes acceptance of nextmedia's Privacy Policy and Terms & Conditions.