ATO hardware costs $42m above Change budget

 

Offset by talking down mainframe costs.

The Australian Taxation Office completed its Change transformation approximately $42 million over budget for IT hardware, but clawed back the cost overrun by driving a hard bargain on mainframes.

A benefits realisation assessment (pdf) of the project, conducted by consultancy CPT Global, provides a fascinating glimpse into the inner workings of — and cost breakdowns for — the massive tax project.

While the final cost of the program — $814.6 million — came above the 2010 revised business case budget of $781.3 million, CPT notes the variance is "well within estimating tolerances of a program of this complexity and extended timeframe".

In other words, any over-budget aspects were minor.

However, the fact some cost overruns were related to hardware required for the project is new.

A breakdown of the $814.6 million spent by the department shows that hardware costs — which include mainframe, midrange and WAN equipment — came in at $139.4 million, or 17 percent of the total project cost.

Of the other IT elements, software such as Siebel CRM cost $29.7 million, and $12 million was spent on "ICT concept briefs". Both came in under budget.

However, a further breakdown by CPT shows that the hardware costs were $42.4 million — or 44 percent — above what the ATO had budgeted for.

"The increase in hardware costs relate to a combination of factors including an expectation of reduced capacity combined in mainframe and static midrange and storage expectations, and the extended time of the [Change] program [from four to seven years]," CPT notes.

Because the Change Program replaced a number of legacy systems, the ATO had hoped to achieve a 20 percent reduction in mainframe capacity it used, saving $19.3 million a year.

The department appears to have failed that objective as "infrastructure processing requirements... increased overall", principally because not all legacy tax processing systems were moved across to the new Integrated Core Processing (ICP) platform created under the Change program.

The mainframes also picked up online services and portal workloads that "were not specifically provisioned for", offsetting some of the potential efficiencies expected in the original business plans.

The ATO's saving grace was in its negotiation skills, having driven down the cost of buying mainframe processing capacity by 40 percent since 2004.

"These unit cost reductions completely offset the higher than planned mainframe usage, with a net overall saving to the ATO relative to the 2004 mainframe processing costs," CPT notes.

"However as this reduction has been due to improved commercial terms for mainframe capacity, rather than the expected reduction in the capacity required, we have considered this a zero benefit attributable to the Change Program."

Four-year return

Overall, CPT Global estimates a four-year return on investment on ATO's financial contribution to the project.

The ATO stumped up $597 million of the total $814 million budget, with the remainder coming from Government.

Tangible financial benefits were "conservatively estimated" at between $147 million and $153 million a year.

Although this was lower than initially expected, CPT notes that a large number of intangible benefits have been realised, and that "further benefit realisation" is also possible, including in the areas of business intelligence and data analytics.

The analysis also notes the importance of achieving benefits and value rather than focusing too heavily on "cost control".

Copyright © iTnews.com.au . All rights reserved.


ATO hardware costs $42m above Change budget
 
 
 
 
Top Stories
Review: Microsoft Surface Pro
A year is a long time in the computer hardware business.
 
 
NBN Co could miss revised June fibre targets
Analysis: Cutting it fine in the race to the line.
 
 
Sign up to receive iTnews email bulletins
   FOLLOW US...

Latest VideosSee all videos »

iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
iTnews Academy: Microsoft Windows Server 2012 - Hyper-V
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Australia's 'cloud-last' policy is dangerous.
Interview: Vivek Kundra on Australia's 'cloud last' policy
Bankwest builds continuous delivery capability
Bankwest builds continuous delivery capability
To automatically deploy test/dev sandboxes by mid-year.
Veterans' Affairs sets sights on modernisation
Veterans' Affairs sets sights on modernisation
Data safe with Human Services, CIO says.
Citi Australia drops platform customisations
Citi Australia drops platform customisations
Technology chief shifts focus from building to leveraging systems.
VicRoads restructures IT team
VicRoads restructures IT team
Department moves to align with industry benchmarks.
Zurich Australia extends IT team offshore
Zurich Australia extends IT team offshore
Malaysian staff served from Australian data centres.
Leigh Berrell - Utilities CIO of the Year
Leigh Berrell - Utilities CIO of the Year
Yarra Valley Water CIO Leigh Berrell accepts his Benchmark Award for Utilities CIO of the Year.
Wayne McMahon - Retail CIO of the Year
Wayne McMahon - Retail CIO of the Year
Domino's Pizza CIO Wayne McMahon accepts his Benchmark Award for Retail CIO of the Year.
Inside Perpetual's ongoing IT transformation
Inside Perpetual's ongoing IT transformation
CIO Jenny Levy discusses how outsourcing will help the firm "simplify, refocus and grow".
Managing Complexity - Defence's Daniel McCabe
Managing Complexity - Defence's Daniel McCabe
Daniel McCabe, Assistant Secretary of Australia's Department of Defence, provides the audience at the iTnews Data Centre Strategy Summit with a deep dive into the organisation's data centre consolidation program.
How Facebook designed the data centre from scratch - Marco Magarelli
How Facebook designed the data centre from scratch - Marco Magarelli
The full keynote by Facebook data centre architect Marco Magarelli at the Australian Data Centre Strategy Summit. Magarelli details the design considerations behind the social network's Prineville, Oregon; North Carolina and Luleå, Sweden data centres.
Modernising Legacy Data Centres - Telstra's Jon Curry
Modernising Legacy Data Centres - Telstra's Jon Curry
Telstra general manager of managed data centres Jon Curry guides the audience at the iTnews Australian Data Centre Summit through the build of the telco's Clayton, Victoria data centre.
NSW Government launches NABERS data centre rating tools
NSW Government launches NABERS data centre rating tools
Matthew Clark from the NSW Department of Environment guides facilties managers through the details of the new NABERS data centre energy rating tool at the Australian Data Centre Strategy Summit.
NABERS launch panel: Australian Data Centre Strategy Summit
NABERS launch panel: Australian Data Centre Strategy Summit
Matthew Clark (NSW Dept of Environment), Greg Boorer (Canberra Data Centres), Glenn Allan (National Australia Bank), Mike Andrea (Strategic Directions) and Bob Sharon (Green Global Consulting) discuss the impact of the NABERS data centre rating.
Judges notes: Fortescue Metals [The Benchmark Awards]
Judges notes: Fortescue Metals [The Benchmark Awards]
iTnews' panel of judges discuss Fortescue Metals 'New World of Work" project, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Retail [The Benchmark Awards]
Judges notes: Retail [The Benchmark Awards]
iTnews' panel of judges discuss the shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: Pacific Aluminium [The Benchmark Awards]
Judges notes: Pacific Aluminium [The Benchmark Awards]
iTnews' panel of judges discuss Pacific Aluminium's lightning fast service desk refresh, one of three shortlisted finalists for the Industrials category of the CIO Benchmark Awards.
Judges notes: Domino's Pizza [The Benchmark Awards]
Judges notes: Domino's Pizza [The Benchmark Awards]
iTnews' panel of judges discuss Domino's Pizza's shift to hosted services, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Judges notes: McDonald's Australia [The Benchmark Awards]
Judges notes: McDonald's Australia [The Benchmark Awards]
iTnews' panel of judges discuss McDonald's Australia's new self-service portal for employees, one of three shortlisted finalists for the Retail category of the CIO Benchmark Awards.
Latest Comments
Polls
Will you quit any cloud services in light of PRISM?

   |   View results
Yes
  60%
 
No
  40%
TOTAL VOTES: 92

Vote